HYUNDAI’S U.S. HQ MEETS EXHAUST SHAFT CODES USING AEROSEAL®

Rajeev Nedumaran • Jul 02, 2022

HYUNDAI U.S. HEADQUARTERS

HYUNDAI’S U.S. HQ MEETS EXHAUST SHAFT CODES USING AEROSEAL

HYUNDAI’S U.S. HQ MEETS EXHAUST SHAFT CODES USING AEROSEAL


The new Hyundai U.S. corporate headquarters was scheduled to open for business in just a few weeks. The finishing touches were being made to the interior of the 6-story, 500,000 sq. ft. building in Fountain Valley, California. No one was happy to learn that building engineers could not get official sign-off for the project because of duct leakage in the structure’s four smoke evacuation shafts and an outside air shaft.


Options for reducing the leakage and getting the shafts to meet code were examined. One option included using spray foam to seal visible leaks in the drywall interiors. But this would take months to accomplish, cost as much as $1,000,000, and there would be no guarantee spray foam would sufficiently reduce leakage. Then another option was found — Aeroseal duct sealing technology. Glumac had used the Aeroseal technology for a similar project in Las Vegas with successful results.


PROJECT OVERVIEW


BUILDING

Hyundai U.S. Headquarters


LOCATION

Fountain Valley, California


AEROSEAL CONTRACTORS

Healthy Homes 4U (a.k.a. Aeroseal West Coast)


CONTRACT ENGINEER

Glumac


GOAL

Meet required duct sealing codes for commercial new construction project


BEFORE AEROSEAL

14,861 CFM of leakage


AFTER AEROSEAL

808 CFM of leakage


RESULTS

95% leakage reduction to meet building code for 5% or less leakage and finish the project on schedule


Options for reducing the leakage and getting the shafts to meet code were examined. One option included using spray foam to seal visible leaks in the drywall interiors. But this would take months to accomplish, cost as much as $1,000,000, and there would be no guarantee spray foam would sufficiently reduce leakage. Then another option was found — Aeroseal duct sealing technology. Glumac had used the Aeroseal technology for a similar project in Las Vegas with successful results.


It took the Aeroseal contractor only a couple of weeks to complete all five shafts. Leakage rates were reduced from 20% to 1.1% – well below current code requirements. The cost was just a fraction of the next lowest cost alternative. Best of all, the work was completed in time and Hyundai’s new U.S. corporate headquarters opened on schedule.

I focus exclusively on healthcare facilities and I think that any one of my clients would have an application for this technology. If this (sealing project) was done manually, it would have potentially taken weeks rather than a couple of days to complete.

-Brian Berg, Engineer of Record, Glumac

To Learn More About Improving The Comfort, Indoor Air Quality, and Energy Efficiency Of Your Building Call 0226759426 or Email info@aeroseal.nz

24 Aug, 2023
Leading the charge in energy conservation and indoor air quality improvement, Weis Markets, a prominent Mid-Atlantic supermarket retailer, is making strategic strides. The retailer has embraced cutting-edge technology by adopting the Aeroseal duct sealing solution.
Achieving Optimal Indoor Air Quality: A Medical Facility Case Study
23 Jul, 2023
Learn how Aeroseal helped Seal ductwork to 97% leakage reduction; Save $22,694 in annual energy usage/cost at a New York Medical Facility.
Duct Sealing: Boosting Energy Efficiency and Reducing Costs.
04 Jul, 2023
Are your energy bills skyrocketing? Are you constantly adjusting the thermostat, yet still feeling uncomfortable in your own home? If so, you may be overlooking a critical area of energy loss in your house - your ductwork. Read on to find out how you can reduce your costs and increase effeciency by sealing your ducts.
More Posts
Share by: